Padubidri: Fishing boat capsizes; all 7 fishermen on board rescued Alleged atrocity on lawyer: Punjalakatte SI suspended Moral policing at jewellery shop: 4 arrested Bajrang Dal activists try to assault youth, girlfriend in Mangaluru SC to hear Bilkis Bano’s plea against release of 11 convicts on 13 Dec Nusrat Noor: First Muslim Woman to Top Jharkhand Public Service Commission
Latest News:
Padubidri: Fishing boat capsizes; all 7 fishermen on board rescued Alleged atrocity on lawyer: Punjalakatte SI suspended Moral policing at jewellery shop: 4 arrested Bajrang Dal activists try to assault youth, girlfriend in Mangaluru SC to hear Bilkis Bano’s plea against release of 11 convicts on 13 Dec Nusrat Noor: First Muslim Woman to Top Jharkhand Public Service Commission
Kundapura, 27 July 2021 [Fik/News Sources]: The multi-crore rupees underground drainage (UGD) works here, going on for the past few years, is being further delayed due to land acquisition problems.
The land acquisition process for the works began in 2010. Later when grants from the Centre was cancelled the State government came in for the land acquisition.
In 2014, the town council pledged to give land for STP and wet well construction within six months. Accordingly, the tenders were processed and the order was issued in November 2015. Work began in May 2016, but the town council had not handed over land for the works.
Meanwhile, the contractors were issued notices twice for halting the works but they replied that without the availability of land they cannot continue the works.
Engineers from Karnataka Urban Water Supply and Drainage Board had arrived recently and checked the problems and also held meeting with the officials and members of the town council.